Landlords can now complete the Complaint Handling Code Annual Submissions form. More information is available online.

Clarion Housing Association Limited (202102330)

Back to Top

REPORT

COMPLAINT 202102330

Clarion Housing Association Limited

2 February 2023


Our approach

 

The Housing Ombudsman’s approach to investigating and determining complaints is

to decide what is fair in all the circumstances of the case. This is set out in the

Housing Act 1996 and the Housing Ombudsman Scheme (the Scheme). The

Ombudsman considers the evidence and looks to see if there has been any

‘maladministration’, for example whether the landlord has failed to keep to the law,

followed proper procedure, followed good practice or behaved in a reasonable and

competent manner.

 

Both the resident and the landlord have submitted information to the Ombudsman

and this has been carefully considered. Their accounts of what has happened are

summarised below. This report is not an exhaustive description of all the events that

have occurred in relation to this case, but an outline of the key issues as a

background to the investigation’s findings.

The complaint

1. The complaint is about:

a.  The landlord’s response to the resident’s concerns about his building’s

External Wall System (EWS1) certificate rating.

b. Its response to the resident’s enquiries about the remedial work required for

the building to meet adequate safety standards and the timeframe within

which this is expected to be achieved.

c.  The landlord’s response to the resident’s enquiries about whether the

expected costs of remedial works will be passed onto residents.

 

Background and summary of events

Background

2. In January 2020, the government’s Ministry of Housing, Communities and Local Government (MHCLG) issued revised guidance on building safety standards for flats within apartment blocks – “Advice for Building Owners of Multi-storey, Multioccupied Residential Buildings”. As a result, buildings of any height were potentially in scope for requiring an external wall fire review and completion of an EWS1 (external wall system) form devised by the Royal Institution of Chartered Surveyors (RICS).

3. EWS1 certification required a new assessment of the building by a qualified, independent professional to establish if the external wall system met new fire risk standards, or whether remedial work was needed.

4. The landlord’s Fire Safety Policy states that the aims and objectives of Clarion is to maintain a safe environment and reduce the risk of fire to tolerable levels through various ways including “to reduce the risk of fire to as low as reasonably practicable, for the safety of all residents, staff, contractors and visitors”.

Summary of Events

5. The resident is a shared-ownership leaseholder of the landlord, and his property is a flat in a new-build low rise block, below 18 metres. The development comprises two detached buildings, one with two blocks and the other with three, none over 18 metres.

6. The landlord commissioned consultants to undertake an external façade review and production of an EWS1 form. The consultants visited on 16 September 2020 and on 12 November 2020 it produced the report. The report noted:

a. The aim of the report was to provide a holistic fire safety review of the property, in line with the government guidance of January 2020. Its overall view was that the external wall systems that were present had a detrimental impact on the overall fire safety of the building and did not comply with the government advice.

b. The external façade consisted of brickwork, high pressure laminate (HPL) cladding and steel balconies. The HPL cladding to sections extended the height of the property; behind the HPL is a Celotex insulation, which along with the HPL is combustible. This presented an unacceptable risk of external fire spread. Remedial action was required to remove and replace the HPL system with materials achieving Euroclass A2 or better.

c. Its current RICS EWS1 form rating was B2 meaning that an adequate standard of safety was not achieved, and remedial and interim measures were required. Option B was for buildings where combustible materials were present in the external walls.

7. It is understood that during February 2021 the resident made enquiries about selling his property. As he was not happy that the landlord did not confirm how and when the sale could proceed, he approached his councillor for assistance.

8. On 11 February 2021 the landlord wrote to the resident advising of the consultant’s findings of 12 November 2020. It advised that it was reviewing all its buildings that required similar assessments as well as other buildings where it was aware that works were needed, starting with those that were considered high-risk first.

9. On 18 March 2021 the councillor wrote to the landlord on behalf of the resident.

He noted that the resident had received the EWS1 form and asked the landlord to

confirm what a B2 rating meant, whether there was a programme of works for the

building and how much would it cost. He noted that the resident needed to move

for family reasons and therefore for the works to take place before they could

safely sell their property.

 

10. On 26 April 2021 the landlord wrote to the councillor outlining the outcome of the

EWS1 report of 12 November 2020 and stating that it was required to prioritise

remedial works to its higher risk buildings first, and therefore was unable at that

time to provide a timeframe for works at the resident’s property. With regards to

whether it would pass on costs to shared-owners and leaseholders, it noted that

only buildings over 18m tall were eligible for the Government’s Building Safety

Fund, and it was likely that the terms of the lease would apply. In response, on

26 April 2021 the councillor advised that several residents on the estate were

unhappy that there were no timescales for “remediation” and no advice on the

estimated costs to leaseholders. He stated he would like to escalate each case

to Stage 2 of the Complaints Procedure as it was not right for residents to be just

left waiting.

 

11. On 19 May 2021 the resident emailed that landlord with queries about the EWS1

assessment for his block, the timeframe provided to carry out all the EWS1

surveys and the provision of remedial works as a result of the assessment for his

block.

 

12. The landlord registered a formal Stage 1 complaint due to the recent contact from the councillor, this Service and the resident on 19 May 2021, and on 21 May

2021 sent the Stage 1 response. It stated:

 

a. Without the new EWS1 form, lenders may decline to offer a mortgage or remortgage on a property. The provision of a EWS1 form was not a mandatory

requirement. However, it had instructed EWS1 surveys when requested, when they met the criteria stipulated by RICS, to support homeowners to sell their homes or re-mortgage.

 

b. The EWS1 was instructed on the resident’s estate, as one of the residents

had requested the form for this purpose.

 

c. It was currently completing a national survey of its stock, which would be

completed by the end of this year. Following the completion, a programme of

further investigation and remediation work would be developed, with the

buildings posing the highest risk being prioritised. At that stage, it was not yet

in a position to provide details outlining the nature and extent of the works

which may be required, or an exact date for when identified works may be

completed at the resident’s block.

 

d. It recognised this matter would be of concern to those living at the resident’s development and wished to assure residents that it remained committed to ensuring that any remedial works or upgrades to meet current fire safety standards were delivered as soon as possible. In addition, it would explore all avenues available to minimise the level of any costs that may be recharged to leaseholders; however, it was unable to provide specific details of this at this very early stage.

 

13. On 21 May 2021 the landlord also wrote to the councillor notifying him of the

outcome of the EWS1 assessment for 12 November 2020 and reiterating the

advice that it provided in the Stage 1 response to the resident.

 

14. On 21 May 2021 the councillor, copying in the resident, advised the landlord that

he remained dissatisfied that the landlord did not provide specific information or

timescales for the surveys to be completed and the resulting remedial works and

costs. In a further email sent on 22 May 2021, the councillor reiterated his view

that it was unacceptable that residents would have to wait until December for

answers on remediation works. He also queried how long thereafter it would take

to form a programme of works after the survey.

 

15. On 1 June 2021 the resident emailed the landlord noting:

 

a. He (and other residents) had approached the councillor as his “numerous”

emails and phone calls were ignored and not responded to within the

timeframe provided.

 

b. He had initially called in February 2021 for advice on how to sell his property. The Sales Team’s number did not work so he had to call the Customer

Service team who advised someone would respond in due course. After

receiving no response, he followed the sales advice on the website and paid

for a RICS survey costing £300. However, after sending the landlord the

relevant forms, he was told the EWS1 form was not “up to scratch”. The

landlord also would not tell him why a neighbouring property was up for sale.

 

c. In response to a further email he sent on 19 February 2021, the landlord

advised him that it was unable to market his property until it had completed

outstanding works to the cladding on his block. It hoped the works would be

completed “swiftly”. The resident stated the email correspondence raised his

expectations at that time that the works would be completed. The resident

also noted that he had asked whether he would be compensated the £300 he

paid for his survey.

 

16. The landlord on 23 June 2021 advised that it would escalate the complaint.

 

17. On 26 July 2021 the landlord sent the Stage 2 response. It reiterated the Stage 1

response and added:

 

a. Its consultant had undertaken the initial assessment of the resident’s

development that was being used to form the priority for future intrusive

inspections. This programme of initial assessments was not yet concluded

and was expected to continue for another 3-4 months before all blocks had

been reviewed. However, based on the feedback from the consultant, it was

likely that the block would be classified as a higher priority for the pending

intrusive inspections. It was unable at that stage to confirm when the intrusive

survey would be undertaken but would update residents as soon as it was

able to.

 

b. Following the intrusive inspections, a programme for remediation work would be developed. Again, it was unable to confirm at that stage the extent of any works or an exact date for when these would be completed. It would continue to liaise with the residents to update them on any progress when it was in a position to do so.

 

c. In recognition of the delay in responding to the resident’s complaint within the published service level agreement, it would award of £25 compensation.

The landlord’s internal correspondence indicates that the Stage 2 response

was sent to other residents who had also complained.

 

18. The landlord informed this Service on 18 November 2021 when providing

information for this investigation that:

 

a. Once it had completed its national review of all its buildings, which should be by the end of the year, it would be developing a programme of further

inspections and/or remedial works to the buildings that needed it. It

anticipated being able to provide a timeframe of actions by spring 2022. It

would contact residents at the development once it knew when it would be

able to look into the buildings further.

 

b. It could not confirm at that time whether the lease allowed it to recharge

residents if it decided to do so. Such a decision would also be dependent on

any funding that may or may not be available.

 

19. On 10 January 2022, the government withdrew the guidance of January 2020. It

announced: “No leaseholder living in a building above 11 metres will ever face

any costs for fixing dangerous cladding and, working with Members of both

Houses, we will pursue statutory protection for leaseholders and nothing will be

off the table”. For leaseholders living in buildings below 11 metres, each building

will be assessed on a ‘case by case basis’”.

 

20. On 8 March 2022 the landlord advised the resident that as part of the review of

the external wall system of its properties, it had commissioned a specialist fire

engineer consultant which would be carrying out an intrusive inspection to the

building between 14 and 18 March 2022.

 

21. The specialist consultant found that:

 

a. There was a moderate risk of fire. Accordingly, remedial measures were

required and Option B2 of Form EWS1 would apply to the building at that time

because if any remedial measures at all were required, regardless of scale,

then Option B2 must be selected.

 

b. Although the materials used in the external walls were not in themselves a

concern, there were extensive issues with the standard of installation of cavity

barriers. Therefore, in its opinion, it could not be ensured that there was a

reasonable standard of health and safety for those in and around the blocks.

Remedial measures would therefore be required to reduce the fire risk to a

tolerable level.

 

22. On 14 April 2022 the landlord wrote to the resident advising that whilst the fire

engineer had found that the cladding was of limited combustibility, there was a

defect with the construct of the external wall system that meant the EWS1

continued to have a B2 rating. This would require remediation to bring the

building in line with current fire safety guidance. The landlord further advised that

it would be meeting with the developer to decide the next steps.

 

23. On 22 April 2022 the resident asked the landlord, copying the email to the

councillor, to provide the EWS1 form in full from the recent fire safety inspection.

On 6 May 2022 the landlord wrote to the councillor providing the EWS1 form. It

reiterated that there was a potential issue with the provision of cavity barriers in

the construction of the external wall system that was likely to require remediation

and that it would be meeting with the developer. The landlord reiterated this

advice in a letter sent to the resident dated 24 May 2022.

 

24. On 25 July 2022 the landlord advised the resident that the developer wished to

undertake some sample inspections itself on 3 and 4 August 2022.

 

25. The landlord has since advised this Service that the developer had indicated a

desire to remediate the issues identified by the consultant. It had met the

developer on site to discuss its proposals, and then arranged for it to have

access to the building to undertake its own intrusive inspection. It was now

waiting for a formal proposal in writing, after which it will advise residents. The

landlord has further confirmed its intention regarding the funding of the works.

 

26. The resident has advised this Service that the cavity wall barrier issue was not

raised in the EWS1 form of November 2020 and that he believes the landlord

should not prevent him from selling his property pending works to the cavity wall

barrier.

 

Assessment and findings

 

27. Under the Housing Act 1996 where this Service investigates a complaint, it must

determine it by reference to what is, in the Ombudsman’s opinion, fair in all the

circumstances. In investigating this complaint, we have considered the

Ombudsman’s spotlight report on “Dealing with Cladding Complaints” (May

2021), and the landlord is reminded to refer to the report. Whilst there has been

changes in government guidance since the report, the report identified three key

lessons which still are applicable as the issues with cladding remain and because

many residents consequently are still in a position of uncertainty about their

housing options and financial liabilities.

 

a. What are the landlord’s long-term plans for compliance with the guidance, and are these fair and reasonable? The Ombudsman believes it is essential for landlords to provide a clear road map – with timescales – to all residents. The longer the gap between setting out long-term plans and any progress the less likely it is that this will be considered fair and reasonable.

 

b. How has the landlord communicated with shared owners/leaseholders

regarding the situation, and was this communication appropriate? Effective

communication is vital, and landlords need to assure themselves that their

strategy for this is robust, well-resourced and proactive given the evolving

situation and changing circumstances. The risk otherwise is increased

frustration and deterioration of the resident and landlord relationship.

 

c. How has the landlord responded to the individual circumstances of the

resident? Has the landlord considered the impact of the situation on the

particular circumstances for the resident? The Ombudsman expects a

landlord to show empathy for residents trapped in these circumstances and to

mitigate the impact where possible. Landlords should always address the

individual circumstances presented in a complaint and, where appropriate,

exercise discretion as they would with other complaints. The longer this crisis

continues the greater the impact will be on individuals’ life chances, their

finances, mental health and well-being.

 

The landlord’s response to the resident’s concerns about his building’s External Wall

System (EWS1) certificate rating

 

28. The landlord’s first consultants produced the EWS1 form after it inspected the

external walls at the development in September 2020. The resident enquired

about selling his property from February 2021; however, the landlord was to take

action at the resident’s block based on the findings in the EWS1. Furthermore,

the landlord needed to make a decision on the cost implication for the resident.

Therefore, he could not proceed with the sale.

 

29. The EWSI form had a B2 rating which at the time required it to carry out remedial

works. Given the landlord’s legal and policy obligations to reduce the risk of fire

as low as possible and ensure that the building was in line with fire safety

guidance, it was appropriate that the landlord decided it would make further

investigations at the resident’s development and then carry out remedial works.

 

30. However, the landlord had a wider responsibility to review the fire risk and safety

of buildings across its whole housing stock. Given this wider responsibility and

the need to prioritise its resources, it was reasonable that the landlord decided to

complete the review of all its buildings before carrying out further investigations

and works at the resident’s development.

 

31. The landlord carried out an intrusive survey in March 2022, over a year after its

initial inspections. It is acknowledged that there has been a delay in the further

inspection which has caused delay and frustration to the resident in particular

because he has been unable to sell his property. However, it is also recognised

that the landlord is a relatively large social landlord and that it adopted a riskbased approach to prioritise investigations and remedial works. It is considered

that a risk-based approach to prioritising buildings for inspection considering

height, occupancy and known building materials to be a rational approach to

responding to government guidance. As such it cannot be concluded that the

delay is indicative of service failure by the landlord.

 

32. The further inspection found a new issue with the cavity wall barriers. Although

not a cladding issue, the cavity barrier installation has caused the B2 rating to

remain, therefore it is reasonable that the landlord is proceeding with carrying out

remedial works. It is consulting with the developer over the remedial works which

is reasonable given that the developer was responsible for the construction of the

building and is well placed to understand how the risks identified can be

remedied. Again, it is acknowledged that this process is adding to the delay;

however, again it is not indicative of service failure by the landlord.

The landlord’s response to the resident’s enquiries about the remedial work required

for the building to meet adequate safety standards and the timeframe within which

this is expected to be achieved

 

33. The landlord initially advised the resident in February 2021 that it was reviewing

the external walls of all its buildings that required such an assessment. Over the

next three months the resident and the councillor on his behalf understandably

asked the landlord to provide timescales for completing the surveys of its

buildings and for carrying out works at the resident’s building, culminating in the

landlord registering a formal complaint.

 

34. As noted above, it is important that landlords communicate effectively and

provide timescales for the action being taken to resolve cladding and fire safety

issues. In this case, it was not until the Stage 1 response of May 2021 that the

landlord indicated that building surveys were anticipated to be completed by the

end of the year, after which further investigations and works could be prioritised

and carried out. At the time this was a reasonable response as the landlord

confirmed the process that needed to be followed before works to the resident’s

building could be specified and arranged. It also confirmed when it would be able

to devise a programme of further investigations and remedial works – after the

end of the year when the surveys were completed.

 

35. The landlord confirmed in the Stage 2 response of July 2021 that it was likely that the initial assessment of all its blocks would not be completed until the

November/December of that year, and that a further, intrusive, inspection would

be required at the resident’s development so that remedial works could be

identified.

 

36. However, following the Stage 2 response, the landlord did not update the

resident, either directly or through the councillor, until March 2022 when it

confirmed the dates the intrusive inspection would take place. As noted, it had

indicated that the initial review of all its stock would be completed by or during

December 2021. It was therefore unreasonable that the landlord did not provide

an update to the resident at this time, for instance to confirm whether the

timeframes for action previously provided still held.

 

37. Aside from not confirming whether timeframes previously given were being met, it was unreasonable the landlord did not make contact with the resident sooner and

more regularly. The Ombudsman’s Spotlight Report states that “Landlords must

ensure that they are proactive in providing appropriate and timely updates on a

regular basis, at least once every three months even where there is little or no

change”. The landlord did not do this. Essentially, the landlord did not take

sufficient steps to assure the resident that it was taking the necessary action, as

promptly as possible, to bring his complaint to a final resolution.

 

38. Furthermore, the Spotlight Report states that landlords should show empathy for

the resident’s situation, mitigate the impact where possible and address the

individual circumstances of the complaint. In this case, the landlord was aware of

the resident’s frustration that the sale of his property was being put on hold

pending identification and completion of the remedial work, and therefore that he

felt trapped in his property. However, it failed to acknowledge the circumstances

of the resident’s case and the impact on him, including the resident’s claim for

reimbursement of a survey he paid for; in fact, the landlord’s responses and

updates were generic. The resident has further stated that he has made

suggestions to the landlord which have not been responded to, such as being

allowed to sell his property despite the cavity wall issue and the landlord buying

his property back.

 

39. As noted above it is reasonable that the landlord consults with the developer but

at present the landlord is awaiting a proposal from the developer. According to

the information provided to this Service by the parties, the landlord has not

indicated to the resident when it has requested or expects the developer’s

response and therefore when the completion of any identified works can

commence. Therefore, the resident’s uncertainty is continuing.

 

40. This Service notes that the landlord has recently advised that it will be providing a further update to residents by the end of September 2022, pending a written

proposal from the developer. To mitigate the resident’s uncertainty the

Ombudsman orders the landlord to provide an update with timescales for further

action by the end of September 2022 regardless of whether it has heard back

from the developer.

 

The landlord’s response to the resident’s enquiries about whether the expected costs of remedial works will be passed on to residents.

 

41. The landlord initially advised the resident and the councillor in April 2021 that as

there was no government funding for works to buildings under 18 metres, it was

likely that the resident would have to contribute to the cost of remedial works as

per the conditions of his lease. The landlord’s response at Stage 1 further

indicated that costs “may” be recharged to resident.

 

42. Whilst the landlord’s advice reflected its understanding that there was no external

funding of remedial works at that time, it did not say with certainty that the

resident would have to bear all or part of the cost. This in itself was not

unreasonable as the issue of the completion and funding of remedial works was

evolving and required ongoing review by the landlord. However, the landlord then

had a responsibility to update the resident and as noted above, every three

months is a reasonable period.

 

43. Thereafter there is no evidence that the landlord updated the resident about the

cost of remedial works and liability, which has prolonged his uncertainty. The

landlord’s advice to this Service of November 2021 indicates that it was still

undecided on whether to recharge leaseholders, and the availability of funding

would affect the decision. However, there is no evidence that this was

communicated to the resident.

 

44. It was also unreasonable that the landlord did not provide an update to the

resident after the government announcement of 10 January 2022. Although the update itself may not have been significant to the resident as their building stands below 11 metres in height; this does not negate the landlord’s responsibility to provide proactive, meaningful updates. Whilst the content of the announcement had not been passed into law, the government intended to ensure that leaseholders in buildings above 11 metres would not face costs for cladding. While this does not apply to the resident’s block, the landlord should have updated them and informed them of why the latest government guidance would not apply to them. As such it was unreasonable that the landlord did not contact the resident to acknowledge the change in government policy and the possible implications for him.

 

45. There is also no evidence that the landlord has provided clarification on whether

residents will be expected to pay for the works to the cavity barriers which are

separate to cladding works and therefore not covered by the government

announcement of 10 January 2022. This too has contributed to the resident’s

uncertainty about costs. The landlord has advised this Service in recent

correspondence that it has now made a decision on recharging residents, and it

is ordered that it communicates this position in the update to be provided by the

end of September 2022.

 

Determination (decision)

 

46. In accordance with paragraph 54 of the Housing Ombudsman Scheme, there

was no maladministration by the landlord in respect of the landlord’s response to

the resident’s concerns about his building’s External Wall System (EWS1)

certificate rating.

 

47. In accordance with paragraph 54 of the Housing Ombudsman Scheme, there

was maladministration by the landlord in respect of its response to the resident’s

enquiries about the remedial work required for the building to meet adequate

safety standards and the timeframe within which this is expected to be achieved.

 

48. In accordance with paragraph 54 of the Housing Ombudsman Scheme, there

was maladministration by the landlord in respect of its response to the resident’s

enquiries about whether the expected costs of remedial works will be passed on

to residents.

 

Reasons

 

49. Following the initial B2 rating on the ESW1 form it was appropriate that the

landlord decided it would make further investigations at the resident’s

development and then carry out remedial works. However, it was reasonable that

the landlord decided to complete the review of all its buildings, following a risk

based approach, before carrying out the further investigations and works at the

resident’s development. It is also reasonable that the landlord is proceeding with

carrying out remedial works based on the B2 rating from the EWS1 form of March

2022, and consulting with the developer about these works.

 

50. Following the Stage 2 response it was unreasonable that the landlord did not

provide more prompt and regular updates to the resident about the progress of

inspections and remedial works, and timeframes involved. Essentially, the

landlord did not take sufficient steps to assure the resident that it was taking the

necessary action, as promptly as possible, to bring his complaint to a final

resolution. Furthermore, the landlord has failed to acknowledge the

circumstances of the resident’s case and the impact on him, including the

resident’s claim for reimbursement of a survey he paid for; in fact, the landlord’s

responses and updates were generic.

 

51. After sending the Stage 1 response, there is no evidence that the landlord

updated the resident about the cost of remedial works, which has prolonged his

uncertainty. It was also unreasonable that the landlord did not provide an update

to the resident after the government announcement of 10 January 2022. There is

also no evidence that the landlord has provided clarification on whether the

resident will be expected to pay for the works to the cavity barriers.

 

 

 

 

Orders and recommendations

 

Orders

 

52. The Ombudsman orders that by 7 October 2022:

 

a. The landlord writes to the resident with an update on the remedial works to be completed at his development. The update should:

 

i. Be sent regardless of whether the landlord has received a written proposal by the developer and should provide timescales for courses of further action.

 

ii. Address suggestions received from the resident regarding the resolution of his complaint.

 

iii. Confirm the landlord’s position on whether the resident will be asked to contribute to the cost of remedial works.

 

53. The Ombudsman orders that within four weeks of this determination:

 

a. The landlord sends a written apology to the resident for the failures identified in this report.

 

b. The landlord pays the resident £200 compensation in respect of the distress and inconvenience caused by the failings in its responses to his enquiries about the remedial work and timescales involved.

 

c. The landlord pays the resident £200 compensation in respect of the distress and inconvenience caused by the failings in its responses to his enquiries about whether the expected costs of remedial works will be passed on to residents.

 

Recommendation

 

54.The Ombudsman requests that the landlord confirms its intentions regarding the

following recommendations within four weeks of this determination:

 

a. The landlord reviews whether it has provided an informative, current update to all residents presently affected by ongoing fire safety and cladding issues.

 

b. The landlord reviews its communications strategy on fire safety and cladding to ensure that future developments on this issue are proactively

communicated to residents and this work is appropriately resourced.